Skip to main content
File #: AR-2024-903    Version: 1 Name:
Type: Consent Status: Agenda Ready
File created: 6/12/2024 In control: City Council
On agenda: 7/1/2024 Final action:
Title: Public Works Facility Architectural Design: Code Compliance Update and Coordination with CMAR
Attachments: 1. Schenkel-Shultz Inc 2021800 Edgewater PW Add Serv FP 2024_0612.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

                     COUNCIL AGENDA ITEM

 

SUBJECT:

title

Public Works Facility Architectural Design: Code Compliance Update and Coordination with CMAR

body

 

DEPARTMENT:

Environmental Services

 

SUMMARY:

Design of the Public Works Facility began in February 2021, with a major scope change in May 2023. The City solicited for and selected the Construction Manager at Risk (CMAR) firm in May 2024, with consideration of a proposal to begin CMAR Pre-Construction services appearing on the July 2024 agenda. Due to the length of time since the beginning of the design of the Public Works Facility, the Architect of Record Schenkel-Shultz, Inc. is requesting a change order in the amount of $35,112 to review and update all project documents to ensure compliance with the current versions of the various regulatory codes and standards and to coordinate the documents with the constructability recommendations from the CMAR during their Pre-Construction review.

 

BUDGETED ITEM:                        Yes No Not Applicable

 

BUDGET AMENDMENT REQUIRED:                        Yes No Not Applicable

 

 

RECOMMENDED ACTION:

Motion to approve the proposal from Schenkel-Schultz, Inc. in the amount $35,112.