COUNCIL AGENDA ITEM
SUBJECT:
title
Request approval for the Change Order from Halff Associates, Inc. for the proposed emergency traffic signal at Fire Station 55.
body
DEPARTMENT:
Fire Rescue
SUMMARY:
The City of Edgewater has contracted Halff Associates, Inc. to handle the design work required by the Florida Department of Transportation (FDOT) for an emergency traffic signal in front of Fire Station 55. The original approved proposal and the 1st change Order for this design work was $127,135. However, a change order has been requested, increasing the cost by $56,672 to accommodate additional design work requested by FDOT due to a change in timeline and FDOT standards.
BUDGETED ITEM: ☐ Yes ☒ No ☐ Not Applicable
BUDGET AMENDMENT REQUIRED: ☒ Yes ☐ No ☐ Not Applicable
RECOMMENDED ACTION:
Motion to approve the Change Order from Halff Associates, Inc.in the amount of $56,672 and to authorize the City Manager to Execute the Change Order.