File #: AR-2023-658    Version: 2 Name:
Type: Other Business Item Status: Passed
File created: 12/15/2023 In control: City Council
On agenda: 1/8/2024 Final action: 1/8/2024
Title: Request to Extend Time 30 Days to Clyde Johnson Contracting (CJC) for the YMCA Wind Retrofit Project ITB-23-PR-11
Attachments: 1. 2023 12 14 Change Order Request for Time Extension Clyde Johnson Contracting and Roofing - YMCA Project, 2. HGMP Grant YMCA - Manufacturer Time Frame Delivery of Windows Jan 19_2024, 3. 2023 12 01 E-mail from HGMP Allowing for Extension, 4. YMCA Building Retrofitt Project - Clyde Jonson Contracting

                     COUNCIL AGENDA ITEM

 

SUBJECT:

title

Request to Extend Time 30 Days to Clyde Johnson Contracting (CJC) for the YMCA Wind Retrofit Project ITB-23-PR-11

body

 

DEPARTMENT:

Parks & Recreation

 

SUMMARY:

City Council approved the contract with CJC on November 6, 2023 for the YMCA building wind retrofit project for a new roof, new wind resistant windows and doors. 

 

The contractor has submitted all of the product specifications and has submitted and received the necessary permits.  The contractor has all material on order.  Most all materials are scheduled to arrive onsite the first week in January, except the windows; which are scheduled to arrive January 19, 2024.  The contractor is requesting a 30 day time extension to allow enough time to finish installing the windows.  The City’s grant administrator contacted HGMP and received permission to extend the grant time without penalty. 

 

Staff respectfully requests City Council to waive the liquidated damages as specified in the contract and approve the change order to extend the contract time 30 days.

 

BUDGETED ITEM:                        Yes No Not Applicable

 

BUDGET AMENDMENT REQUIRED:                        Yes No Not Applicable

 

 

RECOMMENDED ACTION:

Motion to approve to waive the liquidated damages and extend the contract for an additional 30 days.