Legislation Details

File #: AR-2026-0222    Version: 1 Name:
Type: Consent Status: Passed
File created: 7/14/2026 In control: City Council
On agenda: 8/3/2026 Final action: 8/3/2026
Title: Award of ITB 26-PW-03 SUNTrail North Segment from SR 442 to Dale Street
Attachments: 1. PDF COPY - sun_trail_north_segment_from_s_r_442_to_dale_street, 2. Garcia Civil Contractors- Response Document, 3. Declaration Statement, 4. Contracts_on_Hand_7.8.pdf, 5. Completed_Work_ (1), 6. Garcia Civil Con - Construction_Agreement_Signed, 7. ITB 26-PW-03 - Notice of Recommendation with Bid Tab, 8. Stanley Consultants - Bid Tabulation (ITB 26-PW-03), 9. Stanley Consultants - Bid Tabulation Letter (ITB 26-PW-03)

                     COUNCIL AGENDA ITEM

 

SUBJECT:

title

Award of ITB 26-PW-03 SUNTrail North Segment from SR 442 to Dale Street

body

 

DEPARTMENT:

Public Works

 

SUMMARY:

The City of Edgewater issued an Invitation to Bid (ITB 26-PW-03) on June 10, 2026 with the sole purpose and intent of obtaining bids from qualified and licensed contractors for ITB 26-PW-03 SUNTrail North Segment from SR 442 to Dale St.  This project is funded by the Florida Department of Transportation

 

This solicitation was broadcast via the City’s E-Procurement Platform, as well as via DemandStar, Beacon Bid, and the State of Florida DMS Office of Supplier Diversity site, published in the Daytona Beach News Journal, and posted in City Hall.

 

On July 9, 2026, seven (7) bids were submitted and 3 no-bids were received.  All seven (7) bids were deemed responsive and responsible

 

The bids were as follows:

 

Vendor                                                                                                                              Total Bid

 

Garcia Civil Contractors                                                                                    $2,766,564.61

GPS Civil Construction Inc                                                                                    $2,925,060.30

Drewry Site Development                                                                                    $2,999,084.23

Masci General Contractor Inc                                                               $3,220,335.36

Sparks Concrete LLC                                                                                    $3,542,922.78

Gibbs & Register Inc                                                                                    $3,673,457.10

Condor Construction Corp                                                                                    $3,786,442.51

 

The Engineering/Consultant Firm, Stanley Consultants, reviewed the bids and recommends award per the stated bid award criteria to the lowest responsible/responsive bidder, Garcia Civil Contractors. The pricing breakdown is attached. Staff concurs with this recommendation

 

BUDGETED ITEM:                        Yes No Not Applicable

 

BUDGET AMENDMENT REQUIRED:                        Yes No Not Applicable

 

 

RECOMMENDED ACTION:

Motion to award and to authorize the City Manager to execute a contract with Garcia Civil Contractors in the amount of $2,766,564.61 for ITB 26-PW-03 SUNTrail North Segment from SR 442 to Dale Street.