Title: Lift Station 11 Rehab - Construction Engineering & Inspection (CEI) Services
Attachments: 1. Mead+Hunt EW Lift Station 11 CEI Proposal 2024-03-26.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

                     COUNCIL AGENDA ITEM

 

SUBJECT:

title

Lift Station 11 Rehab - Construction Engineering & Inspection (CEI) Services

body

 

DEPARTMENT:

Environmental Services

 

SUMMARY:

Constructed in the 1970’s, this project involves the rehabilitation of Lift Station 11 due to the station’s age and condition. The station is located near Park Avenue on Wildwood Boulevard. Upgrades will include the removal and replacement of two (2) pumps, lining the wet well, addition of a valve box with bypass pumping capabilities, new electrical and control panel and installation of a standby bypass pump to provide emergency pumping capabilities.

 

The City’s continuing engineering consultant, Mead & Hunt Inc. completed the engineering design, and permitting of the site and has provided the attached proposal to provide construction phase engineering services, including construction observation.

 

At their February 2024 meeting, City Council awarded the competitively bid construction contract ITB 23-ES-12 to the lowest responsible responsive bidder Clearwater Solutions Inc. in the amount $563,209.05.

 

 

 

BUDGETED ITEM:                        Yes No Not Applicable

 

BUDGET AMENDMENT REQUIRED:                        Yes No Not Applicable

 

 

RECOMMENDED ACTION:

Motion to approve the proposal from Mead & Hunt, Inc. in an amount not to exceed $70,692 for the construction phase engineering services of Lift Station 11.