Skip to main content
File #: AR-2024-1002    Version: 1 Name:
Type: Consent Status: Agenda Ready
File created: 8/16/2024 In control: City Council
On agenda: 9/9/2024 Final action:
Title: Replacement of Water Treatment Generator
Attachments: 1. LET-737-City_of_Edgewater_Water_Plant, 2. 23 - #496 FSA ATS Binder, 3. 24 - #176 500 FSA Land Base Generator Binder
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

                     COUNCIL AGENDA ITEM

 

SUBJECT:

title

Replacement of Water Treatment Generator

body

 

DEPARTMENT:

Environmental Services

 

SUMMARY:

The City of Edgewater owns and operates a water treatment facility, the Alan R. Thomas Water Treatment Plant, which has a 5.0-MGD treatment capacity and currently serves a total of 12,230 connections.

 

As a critically essential facility, the treatment plant is equipped with a standby generator to continue full operations during power outages. The current generator was installed in 1992 and has exceeded its useful life, requiring replacement.

 

The Environmental Services Department has obtained a quote for the fabrication and installation of a Tradewinds Power Corp 500-kW generator with a 600-Amp Automatic Transfer Switch through the competitively priced purchasing cooperative Florida Sheriffs Association Contract (Bid No. FSA23-EQU21.0 Specification No. #176). The total cost of all equipment, engineering, installation, commissioning, and training totals $435,521.

 

 

BUDGETED ITEM:                        Yes No Not Applicable

 

BUDGET AMENDMENT REQUIRED:                        Yes No Not Applicable

 

 

RECOMMENDED ACTION:

A motion to approve the purchase of a replacement generator and automatic transfer switch for the Water Treatment plant from Tradewinds Power Corp through the Florida Sheriffs Association Cooperative Purchasing Program in the amount $435,521.