Legislation Details

File #: AR-2025-0394    Version: Name:
Type: Consent Status: Agenda Ready
File created: 9/23/2025 In control: City Council
On agenda: 10/6/2025 Final action:
Title: G2/G11 Canal Improvement Group B - Design Scope Change #1
Attachments: 1. EW G2 G11 Group B Design Scope Change #1.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

                     COUNCIL AGENDA ITEM

 

SUBJECT:

title

G2/G11 Canal Improvement Group B - Design Scope Change #1

body

 

DEPARTMENT:

Public Works

 

SUMMARY:

This project design needed to be adjusted to accommodate the acquisition of an additional pond site located on Pearl Street for the construction of an additional stormwater pond and relocation of the proposed pump station originally planned to be constructed at the Canal Road pond site. The scope change in the amount of $79,066.00 in addition to the original purchase order for $669,696.00.

The increase will be covered/reimbursable under the $15 million dollar grant being utilized for this project.

 

BUDGETED ITEM:                       ☒ Yes ☐ No ☐ Not Applicable

 

BUDGET AMENDMENT REQUIRED:                       ☐ Yes ☐ No ☒ Not Applicable

 

 

RECOMMENDED ACTION:

Approve the G2/G11 Canal Improvement Group B Design Scope Change #1.